Did Tesla Open New Superchargers Ahead of Thanksgiving Travel?

A Tesla Cybertruck parked near new white Tesla Supercharger stalls in El Dorado Hills, California, with autumn trees on a hillside behind them.

Yes. Tesla Charging, the company’s official charging account on X, said Wednesday, Nov. 25, 2026, that “1,027 stalls across 91 sites opened in the last 56 days, averaging ~18 new stalls a day in the U.S. alone,” as part of its “Preparations for Thanksgiving travel.” The same post listed “Higher uptime and service dispatch ahead of and during the travel window,” “29 mobile stalls strategically deployed for added travel capacity,” “Attendants for queue management at our busiest sites,” and a “Waitlist pilot live at 300 sites.”

Those preparations follow a mid-November run of new U.S. site posts. Tesla Charging listed 15 new U.S. Supercharger sites from Monday, Nov. 16, through Friday night, Nov. 20, 2026. The stall counts in those posts add up to 204, by Redfire’s count. The newest of that group is a 24-stall site in Millbrae, Calif., posted at 10:16 p.m. ET Friday. The Nov. 16 to 20 dates fall inside the 56-day window Tesla cited. Tesla did not publish a full list of the 91 sites or say how the 204 stalls in those mid-November posts relate to the 1,027-stall total.

The mid-November openings are part of what Max de Zegher, who posts as @MdeZegher and says he has been “Building Superchargers since 2014,” called a “big push” by Tesla’s U.S. Supercharger team. Chief Executive Elon Musk reposted the message on Nov. 17.

“Big push underway from the US Supercharger team to open new sites before Thanksgiving travel,” de Zegher wrote on X on Nov. 17, thanking utilities and local inspectors “keeping energizations of this critical infrastructure on track.”

Thanksgiving travel preparations

The “~18 new stalls a day” average is Tesla’s figure. Tesla did not name all 91 sites, break the 1,027 stalls down by state or week, or give numbers for the higher uptime and service dispatch it cited.

A graphic Tesla Charging posted with the Nov. 25 message shows mobile charging units at sites labeled Firebaugh, Calif. (+10 stalls); Bakersfield, Calif., Olive Dr (+8 stalls); Bakersfield, Calif., Copus Rd (+4 stalls); and Holbrook, Ariz. (+7 stalls). Tesla’s post said “29 mobile stalls strategically deployed for added travel capacity.” The company did not say those labeled sites are the full mobile deployment, and it did not say whether the units are temporary.

On Thursday morning, Nov. 26, Thanksgiving Day, Tesla Charging posted, “Charge at any U.S. Supercharger today to earn the Thanksgiving badge.”

The new U.S. Supercharger sites

Tesla Charging listed each location below as a new Supercharger and gave a stall count in the post. California got the most, with five sites. The South added Murfreesboro, Tenn.; Spanish Fort, Ala.; Benton, Ark.; and Centreville, Va. The Northeast added two New York sites, one in New Jersey and one in New Hampshire. Tesla did not say what time each site first took cars or what hours it keeps. This mid-November list is not a second total on top of the 1,027 stalls Tesla cited on Nov. 25.

Site (links to Tesla’s map)StallsTesla Charging post
Murfreesboro, Tenn. (Elam Road)24Mon., Nov. 16, 2:08 p.m. ET
Depew, N.Y.12Mon., Nov. 16, 4:25 p.m. ET
Rochester, N.Y.12Mon., Nov. 16, 6:58 p.m. ET
Cloverdale, Calif.8Mon., Nov. 16, 8:22 p.m. ET
Stafford Township, N.J.8Mon., Nov. 16, 9:39 p.m. ET
El Dorado Hills, Calif. (Vine Street)16Tue., Nov. 17, 12:20 a.m. ET
Barstow, Calif. (1540 East Main Street)16Tue., Nov. 17, 5:57 p.m. ET
Spanish Fort, Ala.8Tue., Nov. 17, 9:10 p.m. ET
North Conway, N.H. (White Mountain Highway)16Tue., Nov. 17, 10:37 p.m. ET
Vacaville, Calif. (Peabody Road)16Wed., Nov. 18, 3:41 p.m. ET
Centreville, Va.16Wed., Nov. 18, 6:21 p.m. ET
Des Peres, Mo.8Thu., Nov. 19, 4:59 p.m. ET
Benton, Ark.16Thu., Nov. 19, 9:28 p.m. ET
Snohomish, Wash. (Cathcart Crossing, Supercharger for Business)4Fri., Nov. 20, 3:53 p.m. ET
Millbrae, Calif.24Fri., Nov. 20, 10:16 p.m. ET
Total, 15 sites204Redfire’s sum of Tesla’s posted counts

The Snohomish, Wash., site at Cathcart Crossing, with 4 stalls, is listed under Supercharger for Business, a site a business buys and Tesla adds to its network. The public Superchargers in the list total 14 sites and 200 stalls. Tesla Charging also posted new sites in Iceland, Hungary, the United Kingdom and Japan that week. Those are not counted here.

On Tuesday evening, Nov. 17, the account also posted a new Megacharger with eight stalls in Mesquite, Texas. Megachargers are built for the Tesla Semi, so it is not in the count. Passenger Teslas use Superchargers. Redfire earlier reported on the Megacharger in Conley, Ga.

Waitlist is live at 300 U.S. sites

Waitlist, Tesla’s virtual queue for Superchargers, is “now live at 300 Supercharger sites across the US,” Tesla Charging said at 5:29 p.m. ET Thursday, Nov. 19. Owners can join it in the Tesla app or on the car’s touchscreen, and Tesla says drivers of other EVs can join through the Tesla app. Tesla’s Waitlist support page describes it as available “at select Supercharger sites.” The Nov. 19 post did not list which 300 sites have it. Tesla Charging’s Nov. 25 Thanksgiving post again said a “Waitlist pilot” was “live at 300 sites.”

Software 2026.44.1 also changed the in-car charging map, which now groups charger pins into clusters as you zoom out. Redfire covered that update in What Is Tesla’s Charger Network View in Software 2026.44.1?

How do I precondition my Tesla battery before Supercharging?

Use the car’s navigation to drive to the Supercharger. Tesla’s owner’s manual says the car “preconditions its high voltage Battery when navigating to Supercharger,” so it arrives at a battery temperature that cuts charging time. Recognized third-party fast chargers also start preconditioning when you set one as the destination in the car. Tesla recommends using Trip Planner to navigate to a charging location for at least 30 to 45 minutes before arrival, in both cold and hot weather. Preconditioning starts when you navigate to the Supercharger, even if Trip Planner is off. If the drive is shorter than that, the manual says to consider preconditioning the battery before you leave. That means scheduled preconditioning, or Climate and Defrost in the Tesla app, which the manual says “also warm the high voltage Battery as needed.” Tesla does not say that path will deliver the same charging speed as navigating to a Supercharger.

The Maps and Navigation chapter says to start that navigation this way:

  1. Touch the search bar on the car’s map, then touch Charging.
  2. Touch the pin for the Supercharger you plan to use. A popup appears.
  3. Touch the arrow icon to start navigation to that Supercharger.

Redfire tip: Keep navigation running until you arrive, so the car can warm the battery on the way.

In cold weather, the motors can hum or whir while the car heats the battery on the way to a Supercharger. Tesla’s Normal Operating Sounds page calls that normal.

On a Cybertruck, navigating to a Supercharger or to a recognized third-party fast charger works the same way. For a third-party charger, set it as the destination, because Trip Planner will not add it as a stop on its own. Twisting red lines next to the battery icon show the battery is warming. Busy Superchargers may cap charging at 80% if you are not using Trip Planner. A Tesla Supercharger needs no adapter.

A manual preconditioning button is not live. It is in Tesla app 4.63.0 code but is not turned on yet, and Tesla has not announced it.

What Tesla has not said

Tesla Charging has now posted Thanksgiving travel preparations, but it has not said how busy highway Superchargers will be over the holiday weekend. It has not posted off-peak charging times, expected waits, or which highway corridors are likely to be busiest. Tesla has not published holiday charging statistics for this year, and it has not listed all 91 sites in the 56-day total, all of the mobile-stall locations, or the 300 sites in the Waitlist pilot. The mid-November site count and stall totals above remain only what Tesla Charging posted as new from Nov. 16 through Nov. 20.

Also in The Brief: How Should You Charge an EV? A Simple Guide for New Owners

FAQ

How many new Superchargers did Tesla open before Thanksgiving 2026?

Tesla Charging said Nov. 25 that “1,027 stalls across 91 sites opened in the last 56 days, averaging ~18 new stalls a day in the U.S. alone.” From Nov. 16 through Nov. 20, the account posted 15 new U.S. Supercharger sites whose stall counts total 204, by Redfire’s count. Tesla did not publish a full list of the 91 sites.

Can I join a Supercharger waitlist?

Yes, at some sites. Tesla Charging said Nov. 19 that Waitlist is “now live at 300 Supercharger sites across the US,” through the Tesla app or the car’s touchscreen. On Nov. 25 it again said a “Waitlist pilot” was “live at 300 sites.”

Is there a precondition button in the Tesla app?

Not yet. It is in Tesla app 4.63.0 code but is not turned on. Navigating to a Supercharger still preconditions the battery.

Sources